Russian Vice Prime Minister Andrei Nikitin and Transport Minister Dmitry Yadrov toured key infrastructure assets along HSR between Moscow and Tver. NPS CEO Alexey Krapivin outlined the construction progress.
The delegation reviewed bridge and approach viaduct girder production at the Selinskoye casting yard. The production technology is certified.
Each reinforced concrete girder weighs nearly 700 metric tons, so they cannot be transported via public roads. To address this, the company builds all casting yards on-site. There will be ten such yards along the future HSR route.
31,000+ workers and ~11,000 units of equipment have already been deployed to build the HSR line. Over a third of them is concentrated on the Moscow–Tver section, which will host comprehensive testing of both the infrastructure and Russia's first domestic high-speed train.