In a Russian First, NPS Installs 700-Ton Bridge Girder on HSR Line

In a Russian First, NPS Installs 700-Ton Bridge Girder on HSR Line

NPS completed a test installation of the project's first 700-ton bridge girder for the Moscow–St. Petersburg HSR line.
6 November 2026
Such structures have never been utilized in Russia before. The girder was fabricated at the Selinskoye casting yard and installed into the span of the nearly 800-meter overpass.

The operation requires pinpoint precision. Two transporters, each boasting a 450-ton lifting capacity, move the girder from the casting yard to the installation site. The vehicles crawl at approximately 4 km/h. The lead and trailing operators must act perfectly in sync, maintaining identical speed and steering angles. Dual-sided cameras assist with navigation and clearance control.

At the installation site, a launching gantry crane takes over the process, securing the girder, positioning it with pinpoint accuracy, and installing it into its final design position. The entire procedure takes around 40 minutes.

Bridges and viaducts will make up nearly a third of the entire Moscow–St. Petersburg HRS route. With trains cruising at speeds of up to 400 km/h, the massive loads require the bridge girders to meet stringent stiffness, strength, crack-resistance, and durability requirements.

Across the entire route, NPS will install more than 4,500 girders with a total weight exceeding 3 million tons.

Russian Railways and NPS are setting up 10 casting yards to fabricate these girders. The Selinskoye casting yard was the first to launch production, supplying finished structures to construction sites in both the Moscow and St. Petersburg directions over distances longer 42 km.