Natsproektstroy Starts Work on Riverbed Footing of the Oka River Bridge

Natsproektstroy Starts Work on Riverbed Footing of the Oka River Bridge

At the bridge construction site in Ryazan, Natsproektstroy is commencing work on the bridge footing in the river channel.  All necessary machinery has been mobilized, sheet-pile cofferdams have been installed, and steel tubular piles have been driven into the Oka riverbed.
21 July 2026
On the right and left banks, footing construction is underway for the elevated part of the bridge. Eight out of the total 28 support structures is ready, and the installation of girder spans has begun.

To date, 21,000 cubic meters of reinforced concrete have been placed, and 420 tonnes of steel structures have been assembled. The overall technical readiness of the facility now exceeds 25%.

The project remains on schedule, with 370 skilled employees and 62 units of specialized equipment deployed on site, operated by the DiM branch Mostootryad-22 and Transstroymechanizatsiya.