NPS unit Transstroymekhanizatsiya has completed the installation and commissioning of a 350 tph asphalt plant on a reconstruction section of the R-256 Chuisky Trakt federal highway in the Altai Republic. The plant will supply the project with locally produced asphalt mixtures.
Modular housing units, a canteen, and a project office have also been commissioned. Near the village of Manzherok, TSM is executing excavation and embankment works, and installing reinforced concrete culverts. Similar earthworks are also underway at interchange No. 2. In addition, pavement construction is underway on the temporary haul road.
Work has also begun on utility relocation, including gas pipelines, communication networks, and power lines. The installation of bored piles for pier foundations is scheduled to begin shortly.
Currently, the project involves 110 units of equipment and more than 360 personnel.