During the construction of the flyover over the MCD-2 railway tracks in the northwest of the capital, NPS teams are finalizing the construction of retaining walls, which are now over 76% complete. The work is being carried out by Mostootryad-4, a branch of Dorogi i Mosty.
A 450m four-lane flyover (3.5km including approaches) over the Rizhsky railway line will link Priorova Street and 8 Marta Street.
It will reduce the traffic load on such congested structures as the Victory Bridge flyover on Leningradskoye Highway and the Alabyano‑Baltiysky Tunnel on the North‑Western Expressway.
Also, crews are constructing the flyover supports, with work currently underway on 6 out of the 9 supports specified in the design. Their readiness ranges from 10% to 80%.
The overall readiness of the project as a whole is estimated at 20%. More than 4,700 cubic metres of reinforced concrete have already been placed. Currently, 67 workers and 18 construction vehicles are engaged on the site.